SmartDCDC-01 / Data hall 01 / PQ test workspace217:46:53 ETDemo dataProduct overview

PQ test workspace

Measurement guide

Evaluate measured values against your operating criteria. Keep the evidence.

Utility incomer · Path A · 480/277 V · 60 Hz · Three-phase wye · 3φ 4-wire · Simulated instruments · Read-only

Capture. Compare. Document.

Run a spot assessment from the demo meter, or import a three-phase measurement snapshot. Results use your operating criteria and keep a reviewable record.

No equipment control

1. Select the evidence

One physical meter location per assessment

Selected measurement pointUtility incomer Path A

AC-A-INCOMER · 480 V L–L · 60 Hz

Active power
949.2 kW
Worst current THD
3.9 %
Data origin
Simulated

The toolbar chooses the path and meter. To see an advisory fire, choose Path A and PDU / rack feed.

Spot PQ assessment

Eight operating checks plus two assessment-readiness checks.

2. Set operating criteria

Advisory limits, editable for your project

Criteria apply only to this assessment and do not change protective-device settings. Flicker, events, transient withstand and long-term compliance need their own completed observation windows and acceptance specifications.
Demand reference & PCC assessment inputs

Criteria apply only to this assessment and do not change protective-device settings. Flicker, events, transient withstand and long-term compliance need their own completed observation windows and acceptance specifications.

No assessment run yet. Run one to see each measured value, criterion and result, and export them as a CSV report or a JSON record.

Assessment history

This page session only · reloading clears it

No assessments yet. A new run freezes the selected evidence and criteria.

Commissioning evidence

Required before connected or contractual acceptance

This workspace evaluates records. It does not create voltage disturbances, operate a load bank, switch a UPS or execute an electrical commissioning procedure.
Not supplied
Instrument & methods
Meter serial, firmware, IEC method class and standard edition.
Measurement chain
CT/VT ratios, polarity, neutral channel and phase mapping.
Time & calibration
Clock source and error, calibration and transducer uncertainty.
Approved test plan
Load steps, battery and bypass transfers with synchronized input and output recordings.

This workspace evaluates records. It does not create voltage disturbances, operate a load bank, switch a UPS or execute an electrical commissioning procedure.